PRODUCTS List+
Industry Info

What should be paid attention to in the work of the drum screener machine of organic fertilizer equipment?

2023/07/10

The drum screener machine of organic fertilizer equipment is a kind of mechanical equipment widely used in many industries, and has a wide range of applications in sorting technology. People who often contact the roller extension in the industry also need to understand it to avoid problems in the use process, so what problems should be paid attention to in the production process of organic fertilizer production line?

1, the roller screen in the screening machine running smoothly, start the feeding and discharging equipment, feed test run.

2. Close the sealing isolation cover after normal discharge (when the sealing isolation cover is working normally, the sealing isolation cover should always be in the closed position).

3. Check the particle size of the sound output and whether there is leakage and dust.

4. Run for half an hour, carefully check each component, find out the problem and deal with it in time

5. Check the operation frequently in the working process of organic fertilizer equipment . If an abnormal operation or abnormal sound is found, stop the check in time to find out the cause and rectify the fault

6. Installation of the screen body of the drum type screening machine. According to the location of the equipment inlet and outlet, determine the installation position of the screen body

7. Insert steel plate. Before installation, insert the steel plate according to the requirements of the equipment installation drawings, and the upper plane of the embedded steel plate should be on the same plane. The mounting unit provides the insert plates and bottom bolts required for installation

8. Install the foundation tray. The two ends of the screen body are installed on the foundation support by lifting, and the installation Angle of the screen body is adjusted according to the design Angle, and finally fixed welding.

9. Connect the feed port and discharge port, and connect the sealing plate supported by the lower part of the screen body.

10. Rotate the drum screen by hand, there should be no excessive resistance or jamming phenomenon, otherwise the cause should be found out in time to adjust.

11. After the roller screen machine leaves the factory, if the installation time is more than 6 months, the bearing of the large shaft must be removed and cleaned before installation, and new grease must be injected.

12. When the drum screen is closed for a long time (more than 30 days), the motor insulation should be shaken to avoid motor combustion.

Roller screen machine is also mechanical, safety is also very important, so be sure to know more about the machine, to avoid problems do not know how to deal with, if there is a problem can be consulted at any time!

Products
Tel
contact
inquiry